Company Projects
Dan Gote Calm Buoy Project
Client: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Location: MMHE Pasir Gudang, Johor.
Scope:
▶ Structural, Piping and Mechanical Works
Year: Nov 16 – Feb 18
Main Contractor: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Host / Owner: SOFEC Inc
FPSO Cendor Phase 2
Client: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Location: MMHE Pasir Gudang, Johor.
Scope:
▶ Fabrication, Installation and Testing of Hull / Vessel Piping Systems in Cargo Tanks, Ballast Tanks, Pump Room, Fwd Pump Room and Main Deck
▶ Facbrication, Installation and Testing of Topside Piping System
Year: Dec 11 – May 14
Main Contractor: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Host / Owner: MISC Berhad / Petrofac (M) Sdn. Bhd
PFLNG Turret
Client: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Location: MMHE Pasir Gudang, Johor.
Scope:
▶ Turret – Structural & Piping Works
Year: Oct 16 – June 17
Main Contractor: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Host / Owner: SOFEC / Petronas Carigali
Malikai TLP Project
Client: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Location: MMHE Pasir Gudang, Johor.
Scope:
▶ Fabrication and Installation of Structural Columns and Pontoon
Year: Mar 15 – Jan 16
Main Contractor: Malaysia Marine & Heavy Engineering Sdn. Bhd.
Host / Owner: Sabah Shell Pretroleum Co. Ltd. / MISC
Panglima Power Major Outage Oct 2017 (HRSG)
Client: Panglima Power Sdn. Bhd.
Location: Telok Gong, Melaka.
Scope:
▶ Conditions Assessment of Complete HRSG & BOP Piping
Supply, replacement of Hanger Supports
▶ Supply of Upgarded HP Desuperheater Spray Control Valve
(Final Stage) & Desuperheater Pipe Spool (P91 Material)
Year: Jan 17 – Nov 17
Main Contractor: HFS – GE Power System Korea.
Host / Owner: Edra Energy
Panglima 720MW CCGT Power Plant Melaka - 2 x HRSG Boiler
Client: Sukwon Idche (M) Sdn. Bhd.
Location: Telok Gong, Melaka.
Scope:
▶ Complete Erection of HRSG Pressure & Non Pressure Part,
Piping & Supports Installation
Year: Jan 02 – Aug 02
Main Contractor: Doosan Heavy Industries Co.,Ltd.
Host / Owner: Siemens Power Generation
Malakoff Prai Power Plant - Major Outage Aug 2017 (HRSG)
Client: Malakoff Power Berhad.
Location: Prai, Penang.
Scope:
▶ Auxiliary Boiler Repair & Maintenance Works.
▶ Engineering, Procurement and Construction of HPHTSH
Semi Harps (Header + Tubes) Replacement
▶ Engineering, Procurement and Construction of HPSH Outlet Pipe
Relocation and Replacement Works.
▶ Supply, Replacement Work of HPSH Bellows
▶ Engineering, Procurement & Construction of HRSG Flow
Corrective Device (Modification to improve HRSG Inlet
Flow Profile)
Year: Nov 16 – Oct 17
Main Contractor: HFS – GE Power System Korea.
Host / Owner: Malakoff Power Berhad
Malakoff Prai Power Plant - Minor Outage Nov 18 (HRSG)
Scope:
▶ Engineering, Procurement and Replacement of Safety
Valve (HPEV119, HPSV191)
▶ Boiler Tube Repair & Replacement for Sampling.
▶ Conditions Assessment of Complete HRSG & BOP Piping
Supply, Replacement Work of Hanger Supports
▶ Auxiliary Boiler Repair & Maintenance Works
▶ CUI Inspection and Repair
Location : Prai, Penang
Year : Nov 18
Host / Owner : Malakoff Power Berhad
YTL Power Seraya - Major Outage Jan 18
Client: YTL Power Seraya Pte. Ltd.
Location: Jurong Island, Singapore.
Scope:
▶ Engineering, Procurement and Construction of Condensate
Preheater (EC-PR3) Harp Replacement Works Unit 40
(6 Harps in Total)
▶ Conditions Assessment of Complete HRSG 40 & BOP Piping
Supply, Replacement Work of Hanger Supports for Unit 40
▶ Engineering, Procurement & Construction of HP Economizer
#4 & IP Evaporator Tube Replacement Works Unit 40
(261 Tubes in Total)
Year: Feb 17 – Aug 18
Main Contractor: HFS – GE Power System Korea.
Host / Owner: YTL Corporation
YTL Power Seraya - Cogen 30 Outage Jul 18 & Aug 18
Client: YTL Power Seraya Pte. Ltd.
Location: Jurong island, Singapore
Scope:
▶ Engineering, Procurement and Construction of Condensate
Preheater (EC-PR3) Harp Replacement Works Unit 30
(6 Harps in Total)
▶ Conditions Assessment of Complete HRSG 30 Supply,
Replacement Work of Hanger Supports for Unit 30
▶ Engineering, Procurement & Construction of HP
Economizer#4 & IP Evaporator Tube Replacement
Works Unit 30(261 Tubes in Total)
Year : Jul 18 – Aug 18
Host/Owner : YTL Corporation
Panglima Power Sdn Bhd
Scope:
▶ Supply of HP & RH Desuperheater Spray Control Valve
Location: Telok Gong, Melaka
Year: 2017, 2018, 2020
Host/Owner: Edra Energy
Panglima Power Major Outage Nov 2019 (HRSG)
Scope:
▶ Supply, Replacement and Adjustment Works of HRSG Pipe
Hanger and Pipe Clamp
Location: Telok Gong, Melaka
Year: Nov 19
Host / Owner : Edra Energy
Malakoff Prai Power Plant - Minor Outage Mar 19 (HRSG)
Scope:
▶ Supply, Replacement Work of HTRH Pipe Bellows
▶ Boiler Tube Repair & Replacement for Sampling
Location: Prai, Penang
Year: Mar 19
Host/Owner : Malakoff Power Berhad
FSO Sao Vang - External Turret
Scope:
▶ Fabrication and Erection of Multi-dicipline Works;
Structural, Piping and Mechanical
Structural, Piping and Mechanical
Location: MMHE Pasir Gudang, Johor
Year: May 19 – Mar 20
Host/Owner : Promor Pte. Ltd. / Malaysia Vietnam Offshore Terminal (MVOT)
Weight Info: 1340 MT
Bekok A & B Project
Scope:
▶ Structural, Piping & Mechanical (Multidicipline Package) og
2 nos of WHP Topside, Jacket and Bridge
Location: MMHE Pasir Gudang, Johor
Year: Jan 20 – Jul 20
Host/Owner: Petronas Carigali
FSO Sao Vang - Vessel RLE & Conversion
Scope:
▶ Repair Life Extension (RLE) & Coversion of Structural & Piping
Works, Forepeak Modification and Turret Integration Works
Location: MMHE Pasir Gudang, Johor
Year: May 19 – Mar 20
Host/Owner: Promor Pte. Ltd. / Malaysia Vietnam Offshore Terminal (MVOT)
Weight Info: 800 MT
Malakoff Tanjung Bin Power Plant
Scope:
▶ Design, Manufacture and Supply of Boiler Tube Shield
Location: Tanjung Bin, Pontian, Johor
Year: Sep 19
Host/Owner : Tanjung Bin Power Sdn Bhd.
Malakoff Prai Power Plant - Major Outage Jan 20 (HRPI)
Scope:
▶ CUI Inspection and Repair for HRSG, BOP
and Aux. Boiler
▶ Aux Boiler Furnance Refractory Repair
▶ Manhole and Platform Installation and Permanent
Support to Baffle Plate
▶ CRSV 191 Safety Valve Replacement
▶ Boiler Tube Repair and sampling
▶ Supply and modification for HTRH Pipe Support and
Hanger Support Adjustment Work
▶ HRSG Blowdown Tank & Aux Boiler Blowdown Tank
Internal Recoating
▶ Service Air Pipe Replacement
▶ To provide fabrication works for intake bar screen for
Prai Power Plant
▶ Supply, Fabricate and Replace/Install Cooling Water
Pump Lines
▶ ST & HRSG Thermowell Cutting, Boring & Re-Welding
▶ Supply, Fabricate and Replace/Install Fire Fighting
Water Lines and Instrument Air Lines
▶ HRSG Valve and Piping replacement
▶ Supply and Deliver Pipe & Fitting for CUI
Location: Prai, Penang
Year: Jan 20 – Mar 20
Host/Owner: Malakoff Power Berhad